Commissioning: Assuring your assets performance
Last year US industry
spent over $600 billion on plant and equipment maintenance. According to
industry experts, at least 33% of such expenditures or $200 billion was wasted.
Other industry statistics suggest that 72% of all failures of plant and
equipment are outlined by infant mortality failure model. About 6% of equipment
shows aging related wear out failure pattern (John Moubray: RCM II). This means
that failures happen in the early stage of assets lifecycle, and interventions,
instead the general believe, at the end of useful life of assets of age related
failures.
Could we align efforts to
reverse these impressive statistics? Current requirements of the industry,
requires efficiencies in every single aspect of your business. Engineering groups
are not an exception. Assets care is the main responsibility of an engineering
unit and with statistics shown, adequate commissioning practices are required
to assure proper performance of equipment on early stage of lifecycle. As part
of a system start up, commissioning has been a tool to identify if assets are
performing as expected according to design criteria. Traditional Commissioning
ensures that the finished facility operates as intended. It uses a programmed
series of design and construction documentation and testing activities that
verify the functional operation of the equipment. It typically checks operating
parameters such as pressure, temperature, minimum and maximum airflow, lighting
levels, electrical amperage and voltage, torque, fluid volumes, and other
thermodynamic measures to confirm that the design intent has been met. Focus of
such commissioning has been only aligned to process parameters and not
equipment condition. CBM (Condition Based Maintenance) is a key element in trend
setting organizations to assure equipment performance is not part of actual failure
probability statistics. Thus adding CBM to enhance commissioning practices will
provide not only assurance of assets delivering operational parameters, but how
the asset is performing to achieve such parameters.
In rotating
equipment, it is not unusual to discover equipment operation problems after a
construction, overhaul of an asset or major renovation project. Some of those
problems are caused by misapplied design, but most of them are caused by latent
manufacturing defects, poor installation practices, and damage incurred during
transportation and handling. As an example, recent experience with new
construction at two NASA Centers and a major facility of another Federal Agency
revealed 85 – 100% of the rotating equipment at the acceptance phase to be
either misaligned, out-of- balance, or contained defective bearings. In most of
the above cases, the faulty equipment would have passed the specified
acceptance criteria. This same equipment would most likely experience premature
failure during actual operation if the problem conditions were not corrected.
Premature failures decrease system safety, reliability, and efficiency, and
often disrupt ongoing critical operations. The costs associated with that
premature failure not only could have been avoided with better acceptance
criteria, but the costs of correcting the problem should be the responsibility
of the contractor.
There is an
exceptionally high cost associated with a bad design, either because the
equipment is unable to properly satisfy function, equipment life is shortened,
or because operations and maintenance cannot be properly performed. Ensuring a
good equipment design can overcome many of these issues, as well as overcome
premature failure to some extent. Recognize that this practice may cause costs
to escalate. Those additional costs must be weighed in relation to the
perceived value and benefits achieved. Preferred approach is to eliminate those
premature failures and achieve those additional benefits without unnecessarily
enhancing the design, and therefore keeping costs to a minimum.
In
summary, commissioning provides partial assurance of your systems performance
and could be enhanced complementing typical operational parameters checklist
with traditional CBM techniques like vibration analysis, thermography, shaft
alignment check, motor current analysis, tribology, non destructive testing, to
create a quantum leap of improvement to current commissioning practices.
By: George Santos Norat, BSEE, PE
12SEP2008
PdMtech, Inc